Photos from the construction site of the residential complex "Svetliy mir "V stremlenii k svetu..." and the January dynamics of construction are already here!
See the photos and read the report on the construction.
Buildings 7 and 8
— Installation of tiles in halls, low-current systems, insulation, and subsystem for a hinged ventilated facade.
— Laying tiles in the bathrooms of apartments.
— Crimping up to the 13th floor.
Building 9
— Adjustment of window fittings.
— Installation of elevators, insulation, and guides for the installation of a ventilated hinged facade from the 15th to the 25th floor, as well as low-current systems from the 2nd to the 25th floor.
— Installation of cold and hot water risers in sections No. 1 and No. 2 on the 25th floor.
— Start of temporary heating.
Pre-school educational facility
— Masonry on the 3rd floor.