In our latest report, we tell you what has changed in the RC “Svetliy mir “V stremlenii k svetu...“ in September.
Buildings No. 7, 8
— Facade works, installation of composite up to the 25th floor, installation of stained-glass windows up to the 16th floor, installation of entrance groups.
Building No. 9
— Facade works, completion of installation works of the hinged ventilated facade, entrance groups, doors.
Buildings No. 7, 8, 9
— Preparation and hydraulic testing of risers.
— Floor screed, caulking holes in flats and common facilities.
— Phase-gate finishing works from the 2nd to the 13th floors, and further from the 14th to the 25th floors: plastering walls, sewing plasterboard sheet in common facilities; laying tiles on staircases.
— Completion of plastering facades.
— Installation of floor panels of internal electrical networks.
— Installation of low-current systems from the 2nd to the 25th floor.
— Assembly of elevator equipment.
Pre-school education facilities
— Painting of decorative plaster.
— Installation of elevator equipment.
— Completion of roofing and screed floors.