We continue to talk about the progress of construction. Read the news from the RC “Svetliy mir “V stremlenii k svetu...” in the report below.
Buildings No. 7 & 8
— Facade works: installation of the composite up to the 25th floor, stained-glass windows on the 16th floor, and entrance groups.
Building No. 9
— Facade works: installation of a hinged ventilated facade, entrance groups, doors.
All buildings
— Preparation and hydraulic testing of risers.
— Floor screed.
— Finishing works from the 2nd to the 25th floor: plastering walls, sewing plasterboard sheets of common facilities, laying tiles on staircases.
— Works on facade plaster.
— Installation of floor panels of internal electrical networks.
— Completion of work on the installation of low-current systems from the 2nd to the 25th floor of all buildings.
— Installation of elevator equipment.
Pre-school education facilities
— Painting of decorative plaster.
— Installation of elevator equipment.
— Roofing and screed floors.
— Landscaping of the house territory.