We have prepared for you a fresh report on the construction dynamics of the RC “Svetliy mir “V stremlenii k svetu...”.
All buildings
— Preparation of hydraulic tests.
— Final floor screed work.
— Plastering of walls, laying tiles on staircases from the 2nd to the 25th floor.
— Works on facade plaster.
— Installation of floor panels of internal electrical networks.
— Installation of low-current systems from the 2nd to the 25th floor.
— Completion of work on the buttons for calling elevator portals.
Building No. 7
— Installation of composite up to the 25th floor, installation of stained-glass windows on the 16th floor and entrance groups.
Building No. 8
— Installation of composite up to the 25th floor, completion of work on the entrance groups.
Building No. 9
— Completion of the installation of a hinged ventilated facade, entrances, and doors.
Pre-school education facilities
— Plastering of the facade.
— Screed (waterproofing) arrangement.