We have collected for you the news of the outgoing month from the RC “Svetliy mir “V stremlenii k svetu…“. Everything is here, in the new report on the dynamics of construction.
Building No. 7
— Facade works – installation of composite up to the 25th floor, installation of stained-glass windows on the 16th floor, installation of entrance groups.
Building No. 8
— Facade works – installation of composite up to the 25th floor, completion of work on the entrance groups.
Building No. 9
— Facade works – completion of installation works of the hinged ventilated facade, entrance groups, and doors.
Buildings No. 7, 8, 9
— Preparation and hydraulic testing of risers of cold and hot water supplies.
— Final floor screed work (caulking holes in flats and common facilities).
— Installation of floor panels of internal electrical networks.
— Finishing from the 2nd to the 25th floors: plastering of walls, sewing of plasterboard sheet of common facilities, laying tiles on staircases.
— Works on facade plaster.
— Installation of low-current systems from the 2nd to the 25th floor of all buildings.
— The installation of elevator equipment has been completed.
Pre-school educational facilities
— Plastering of the facade.
— Installation of elevator equipment.