RC “Svetliy mir “V stremlenii k svetu...“ in April

03
may 2023

"Svetliy mir "V stremlenii k svetu..."

We are completing a series of Svetlye news about the construction progress. Below you will find out what has changed in the RC “Svetliy mir “V stremlenii k svetu...” by the end of April.

All buildings

— Preparation of hydraulic tests, installation of low-current systems.
— Final floor screed work.
— Finishing works from floor 2 to floor 13, and from floor 14 to floor 25, walls plastering.
— Works on facade plaster.
— Installation of floor panels of internal electrical networks.
— Installation of the curb, preparation of the courtyard area for the first layer.
— Installation of low-current systems from floor 2 to floor 25.
— Installation of elevator portals.

Building No. 7

— Installation of a ventilated facade up to the 25th floor, stained-glass windows from the 2nd to the 16th floor, facades of the 1st floor.
— Laying asphalt parking, installing a curb.

Building No. 8

— Installation of fasteners for the ventilated facade up to floor 25, installation of stained-glass windows from the side of Ilimskaya Street.
— Metal fences and roof construction.

Building No. 9

— Installation of entrance groups and a subsystem of the facade of the ends of the building from the side of Ilimskaya Street and the railway station, installation of corner-stained glass, glazing without shutters.
— Metal fences and roof construction.

Pre-school educational facilities

— Monolithic works have been completed.
— The masonry is made.
— Preparation for facade work.