We continue the reporting week. News about the construction dynamics of the RC “Svetliy mir “Stantsiya “L“...“ in August, see below.
Buildings No. 3 & 11
— Roofing works.
— Installation of doors in basements, on transitional balconies, entrance doors in flats and common facilities.
— Installation of a hinged ventilated facade and stained-glass windows.
— Plastering and insulation of balconies, roof superstructures, descents to the basement, pits.
— Installation of window blocks.
— Screed floors.
— Work on internal power grids.
— Installation of guides, elevator portals, equipment, assembly of cabins, start-revision of elevators.
— Works on internal heating, water supply, and sewerage networks.
— Interior finishing works in the common facilities and residential premises.
Building No. 8
— Pile driving in all sections.
— Preparation for reinforcement and subsequent installation of the foundation of the building.