We have prepared for you a fresh report on the construction dynamics of the RC “Svetliy mir “V stremlenii k svetu...”.
All buildings
— Preparation and conduct of hydraulic tests.
— Floor screed.
— Finishing works on the floors from 2 to 13 and from 14 to 25: plastering of walls, laying tiles on stairwells.
— Works on facade plaster.
— Installation of floor panels of internal electrical networks.
— Installation of low-current systems on the floors from 2 to 25.
Building No. 7
— Installation of composite up to the 25th floor and stained-glass windows on the 16th floor.
— Installation of elevator portals.
— Mounting of input groups.
Building No. 8
— Installation of composite up to the 25th floor.
— Installation of elevator portals.
— Completion of work on the input groups.
Building No. 9
— Installation of elevator portals.
— Installation of hinged ventilated facades, completion of work on entrance groups, installation of doors.
Pre-school education facilities
— Plastering of the facade.
— Screed arrangement.