It's time to take the first look at the construction dynamics of the residential complex "Svetliy mir "Stantsiya "L"..."!
See the photos and read the report on the construction.
Building No. 3
— Concreting of roof exit structures.
— Installation of masonry of internal and external walls in all sections.
— Installation of doors in basements, on transitional balconies, entrance doors in apartments and common facilities.
— Plastering and insulation of balconies, installation of insulation of roofing superstructures from the 8th to the 13th floor in sections 1-4.
— Installation of window blocks.
— Laying the roof of the house.
— Preparatory work for the installation of internal heating networks, water supply and sewerage: breakdown of routes, risers, and installation of technological openings.
Building No. 11
— Masonry of internal and external walls and installation of ventilation units from the 2nd to the 16th floor.
— Installation and installation of window blocks.
— Plastering and insulation of balconies, installation of insulation, door blocks on the transitional balcony, entrance doors in apartments and common facilities.
— Mounting brackets up to the 10th floor.
— Preparatory work for the installation of internal heating networks, water supply and sewerage: breakdown of routes, risers and the device of technological openings.
Extension
— Concreting of vertical structures of the 1st floor, floor slabs of the 1st floor and its parapets.