Here is a fresh report on the construction dynamics of the RC “Svetliy mir “BioPolis ...”.
Buildings No. 1-3
— Works on the wet facade of the building and stained-glass windows.
— Floor screed.
— Laying of the roof.
— Installation of windows.
— Work on internal electrical networks.
Buildings No. 4-6
— Vapour barrier works of the roof.
— Works on the wet facade of the building and stained-glass windows.
— Roofing works.
— Installation of windows.