We publish the latest construction dynamics of the RC “Svetliy mir “BioPolis ...”, see the photos and read the report!
Buildings No. 1-6
— Installation of windows.
— Bricklaying in technical premises.
Building No. 2
— Laying of internal enclosing structures.
Buildings No. 3 and No. 4
— Laying of external and internal enclosing structures.
Building No. 5
— Completion of basement waterproofing with backfill.
— Drilling holes in the roof of sections 3-5.
Building No. 6
— Insulation of the underground part of the building.
— Drilling holes in the roof of the housing.
Boiler house
— Installation of metal structures.
— Moving boilers for installation.