Here, we tell you about the construction progress of the RC “Svetliy mir “V stremlenii k svetu...“. Read the report and see the photo!
All buildings
— Hydraulic testing of risers.
— Final floor screed work, caulking holes in flats and common facilities.
— Finishing works on the floors from 2 to 13, and further the floors from 14 to 25, plastering of the walls.
— Works on facade plaster.
— Installation of floor panels of internal electrical networks.
— Installation of low-current systems on the floors from 2 to 25.
— Installation of elevator portals.
Building No. 7
— Facade works, installation of composite up to the 25th floor, installation of stained-glass windows on the floors from 2 to 16.
Building No. 8
— Work on metal fences and roof construction.
— Facade works, installation of composite up to the 25th floor, installation of stained-glass windows from Ilimskaya Street.
Building No. 9
— Work on metal fences and roof construction.
— Installation of fire compartments on the floors from 3 to 6, installation of entrances and doors.
Pre-school education facilities
— Preparation for facade work.