We have prepared for you a report on the construction dynamics of the RC "Svetliy mir "Stantsiya "L"...".
All buildings
— Monolithic works.
— Roofing works.
— Installation of doors in basements, on transitional balconies, installation of flat entrance doors and doors in common facilities.
— Metal fences and roof structures.
— Cutting and preparation of pipes for heating installation.
Building No. 3
— Installation of masonry internal enclosing structures up to the 15th floor.
— Work is underway on the installation of guides, insulation on the floors from the 2nd to the 16th and on the 25th, installation of a fire cut-off.
— Installation of window blocks.
— Floor screed.
— Installation of guides in elevator shafts, installation of elevator portals, assembly of cabins, start-revision of elevators, installation of equipment.
Building No. 11
— Exterior masonry up to the 25th floor.
— Installation of window blocks.
— Start of floor screed works.
— Guide rails are being installed.