We tell you about the construction dynamics of the RC “Svetliy mir “Skazochnyy les...”. Read the report and see the photos!
Buildings No. 1 and 2
— Plastering of balconies, roof superstructures, descents to the basement, pits.
— Final work on the installation of a hinged ventilated facade and stained-glass windows.
— Screed floors in flats and common facilities.
— Finishing works.
— Assembly of the main switchboards.
— Hydraulic testing of heating systems
Buildings No. 3 and 4
— An individual heat point has been launched in Building No. 3; preparatory work is underway in Building No. 4.
— Assembly of the main switchboards.
— Finishing works and installation of metal doors.
— Screed floors in flats and common facilities.
— Decorative plaster.
— Installation of a ventilated facade.
— Installation of water supply and sewerage, hydraulic testing of the heating system.
Pre-school education facilities
— Installation of stained-glass windows, metal fences and roof structures, hinged ventilated facade.