The latest events in the RC “Svetliy mir “Skazochnyy les...” in terms of the construction progress in our report for July.
Buildings No. 1-4
— Decorative plaster of flat balconies and transitional balconies.
— Installation of a hinged ventilated facade, stained-glass windows.
— Floor screed in flats, common facilities, transitional balconies (caulking holes in floor slabs).
— Completion of roofing works.
All buildings
— Finishing works: laying tiles in bathrooms, common facilities, and elevator halls.
— Assembly of the main switchboards.
— Hydraulic testing of heating systems, installation of drainage, terminal devices.
— Installation of metal doors of flats and common facilities.
Pre-school education facilities
— Installation of translucent structures.
— Installation of a hinged ventilated facade.