New day — fresh news. We have prepared a construction report of the RC "Svetliy mir "Skazochnyy les ..." in April.
Buildings No. 1-4
— Plastering of flat balconies and transitional balconies.
— Installation of a hinged ventilated facade and stained glass windows.
— Floor screed in flats, common facilities, transitional balconies.
— Roofing work.
— Finishing works: laying tiles in bathrooms, common facilities, and elevator halls.
— Assembly of the main switchboards on floors 1 to 5.
— Hydraulic testing of heating systems, installation of VC and terminal devices.
— Installation of metal doors of flats and common facilities.
Pre-school educational facilities
— Installation of translucent structures.
— Installation of metal fences and roof structures.
— Installation of a hinged ventilated facade.