January construction dynamics is a great reason to admire the snow-covered residential complex "Svetliy mir "BioPolis ...". See the photos and read the report on the construction.

Building No. 1: laying of internal enclosing structures and installation of windows.

Building No. 2: completion of monolithic works and installation of ventilation units.

Building No. 3: completion of monolithic works and installation of ventilation units, laying of external and internal enclosing structures.

Building No. 4: production of monolithic works on the 4th floor and completion of work on the insulation of the basement of the building.

Building No. 5: production of monolithic works of the 3rd and 4th floors.

Building No. 6: in sections 1-3, the beginning of the installation of ventilation units and the roof parapet, and in sections 4 and 5 — the construction of monolithic structures of the 4th floor and insulation of the underground part of the building.

Boiler room: foundation construction, development of a trench for laying a gas pipeline from the tie-in point to the boiler room.