On the eve of autumn, news from the RC “Svetliy mir “BioPolis...”: a new report on the construction progress is ready. See below, what has been done in August.
Buildings No. 1-3
— Works on facades of the buildings and stained-glass windows.
— Roofing works.
— Installation of internal power grids.
— Finishing.
— Assembly of water supply and heating systems.
Buildings No. 4-6
— Roof-laying on the buildings.
— Works on the wet facade of buildings and stained-glass windows.
— Installation of windows.
— Finishing.
— Installation of internal power grids.
— Assembly of water supply and heating systems.