We are here to present you the next construction progress report as of April. The RC “Svetliy mir “BioPolis ...” continues to acquire new, important details. What is in progress now, see below.

Buildings No. 1-3

— Laying of the external and internal enclosing structures has been completed.
— Works on the exterior insulation finishing system of the building and stained-glass windows.
— Laying of the finishing layer of the roof.
— Installation of the windows has been completed.
— Floor screed.
— Installation of decking for suspension of elevators.

Buildings No. 4-6

— Laying of the external and internal enclosing structures.
— Completion of work on the vapour barrier of the roof.
— Installation of windows.
— Insulation of the basement.
— Completion of work on the backfilling of the hollows.