We have prepared for you a fresh construction dynamics report of the RC "Svetliy mir "Stantsiya "L"...".
Buildings No. 3 and 11
— Monolithic works.
— Laying of the external and internal masonry.
— Roofing works.
— Installation of doors in basements and on transitional balconies, as well as flat entrance doors and doors in common facilities.
— Installation of insulation and guide facades.
— Plastering and insulation of balconies, roof superstructures, descents to the basement, pits.
— Installation of window blocks on sections 5, 6, and 7 has been completed.
— Work on metal fences and roof structures.
— Installation of guides, elevator portals, assembly of cabins, start-revision of elevators, installation of equipment.
— Floor screed.
— Work on internal power grids and ACEMS.
— Installation of window blocks up to the 16th floor in areas under the lift.
— Cutting and preparation of pipes for heating installation in building No. 3 (section 4).