“Svetliy Mir “Stantsiya “L”...”: construction progress in November

01
december 2022

“Svetliy mir “Stantsiya “L”…”

We open the first winter day with the dynamics of construction of the residential complex "Svetliy Mir “Stantsiya “L”...”! 

Building 3

– Sections No. 1, 2 – concreting of structures on the 16th floor, installation of masonry of internal and external walls from the 2nd to the 9th floor and surface grinding is underway. Installation of ventilation units, staircases, windows on the 1st floor, doors on the transition balcony from the 2nd to the 15th floor continues.

– Sections No. 3, 4 – work is carried out on surface grinding, installation of ventilation units from the 2nd to the 13th floor, staircases, windows on the 1st floor and doors on the transition balcony from the 2nd to the 14th floor.

– Sections No. 5, 6, 7 – internal walls are being installed.

Building 11

– Section No. 1 – masonry construction of internal and external walls from the 1st to the 20th floor, installation of windows and doors from the 2nd to the 11th floor is underway.

– Sections No. 2, 3 – installation of doors in basements, as well as windows from the 2nd to the 11th floor continues.

– Sections No. 4, 6 – work is underway on surface grinding, masonry installation of internal and external walls from the 1st to the 14th floor, cable laying from the 2nd to the 12th floor, installation of doors in the basement and transition balcony from the 2nd to the 15th floor.

– Sections No. 5, 7 – the plaster facade is being installed from the 2nd to the 7th floor, windows are being installed from the 2nd to the 6th floor.