Read the report on the construction progress in December and see the photos.
Building No. 1-masonry of internal and external enclosing structures, installation of ventilation units and installation of windows.
Building No. 2 — backfill and masonry of external and internal enclosing structures, installation of ventilation units.
Building No. 3-masonry of internal and external enclosing structures, installation of ventilation units.
Building No. 4-monolithic works on the 1st-3rd floors, completion of works on insulation of the basement of the building.
Building No. 5-monolithic works on the 2nd floor, completion of work on insulation of the basement of the building.
Building No. 6-insulation of the underground part of the building, installation of ventilation units.
Boiler house — construction of the foundation for a boiler house, development of a trench for laying a gas pipeline.